Chapitre I
GENERAL PROVISIONS
Article 1
The present decree specifies the clauses of application of law n° 2006 / 012 of 29th of December 2006 above mentioned.
Article 2
The prime Minister ensures the highest authority on the partnership contract and withholds on this basis the power of adjudication, (2 ) Notwithstanding the provisions of paragraph 1, The Prime Minister could delegate this power to the person in charge of public contractor having initiated the project.
(3) The signing of the partnership contract depends on the administration, initiator of the project.
Chapitre II
CLAUSES OF THE EVALUATION OF PROJECTS
Article 3
(1) The partnership contract can only be concluded if the project evaluation carried out in view of its eligibility in the system of partnership contract shows, without prejudice other potential criteria, its complex nature and the emergency of realization.
(2)the complex nature of a project is seen as the incapable objective of the public contractor to define, on its own, the appropriate means of satisfying its needs or to evaluate what the market can tender in terms of technical solutions and/or financial or judicial solutions.
(3)emergency is a reason of general interest resulting from the socioeconomic necessity to catch up a delay affecting particularly the realisation of collective equipment or to accelerate growth, in a sector or a defined geographical area.